Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 31 | 31 | 0.000 | 31 | 31.000 | 0.000 |
9W412 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5082/III(2)2023-01(PE)/2023 Lok Niman Anubhag - 02 dt. 09-11-2023
TS Amount (lakhs) : 74.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
74.84
Resanction Cost :
74.84
Tentative Cost :
74.84
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 74.84
Demand : 74.84
Allotment : 74.84
Exp in CFY : 61.30
Total Up to Date Exp : 61.30
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण माह 06/24। दायित्वो का भुगतान शेष।। तीन कार्य 9W411,9W412, 9W413 हेतु एक अनुबन्ध गठित किया गया है। -- as on 05-Jul-2024
Physical Peramenters