Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 31 | 31 | 0.000 | 31 | 31.000 | 0.000 |
9W412 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5082/III(2)2023-01(PE)/2023 Lok Niman Anubhag - 02 dt. 09-11-2023
TS Amount (lakhs) : 74.84 Lacs
Financial Detail
Sanction Cost : 74.84 Lacs
Resanction Cost : 74.84 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 74.84 Lacs
Demand : 74.84 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 1 week ago
09 Nov 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। कार्य प्रगति पर है। तीन कार्य 9W411,9W412, 9W413 हेतु एक अनुबन्ध गठित किया गया है। -- as on 12-Apr-2024
Physical Peramenters