Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.8 | 5.8 | 0.000 | 5.8 | 5.800 | 0.000 |
9W419 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File No 48456 Lok Nimarn Anubagh - 2 dt 15.01.2024
TS Amount (lakhs) : 154.83 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
154.83
Resanction Cost :
154.83
Tentative Cost :
154.83
Exp. Upto Last Fy : 27.67
For CFY 2024-2025
Remaining : 127.16
Demand : 127.16
Allotment : 100.00
Exp in CFY : 32.34
Total Up to Date Exp : 60.01
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 50 %
Sanction on :
6 months 2 days ago
15 Jan 2024
Tentative Completion date:
4 months 19 hours from now
18 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवारो व डामरीकरण का का कार्य पूर्ण। अन्य कार्य स्कपर , पैरापिट , नाली इत्यादित का कार्य प्रगति पर । -- as on 02-Jul-2024
Physical Peramenters