Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 20.46 | 20.46 | 0.000 | 20.46 | 20.460 | 0.000 |
9W420 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : GO No 212/III(2)/2024-01(PE)/2023 dt. 31-01-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 312.09 Lacs
Resanction Cost : 312.09 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 312.09 Lacs
Demand : 312.09 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
आदर्श आचार संहिता समाप्त होने के उपरान्त आवश्यक कार्यवाही की जायेगी। -- as on 12-Apr-2024
Physical Peramenters