Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 64 | 64 | 64 | 0 |
9W422 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 61203 LN Anubagh - 2 dt 30-10-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
9.32
Resanction Cost :
9.32
Tentative Cost :
9.32
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 9.22
Demand : 9.22
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
8 months 2 weeks ago
30 Oct 2023
Tentative Completion date:
1 month 6 days from now
24 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जयो टेक्निकल टेस्ट हेतु निविदा प्राप्त कर कार्य प्रगति पर है। -- as on 09-Jul-2024
Physical Peramenters