Administrative Approval Detail : E-File No 67287 dt. 13-03-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2815.68
Resanction Cost :
2815.68
Tentative Cost :
2815.68
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
2,815.68
Demand :
2,195.00
Allotment :
800.00
Exp in CFY :
24.60
Total Up to Date Exp :
24.60
in Tendering Stage
Sanction on : 8 months 1 week ago
13 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 year 2 months from now
31 Jan 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark