Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7 | 0 |
9W6 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 883/।।।-(2)/08-66 (एम0एल0ए0)/07 दिं0 28.03.08
TS Amount (lakhs) : 245 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
245.00
Resanction Cost :
245.00
Tentative Cost :
245.00
Exp. Upto Last Fy : 234.79
For CFY 2024-2025
Remaining : 10.21
Demand : 35.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 234.79
Work completed
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 100 %
Sanction on :
16 years 3 months ago
28 Mar 2008
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
31 Mar 2024
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
कार्य पूर्ण। -- as on 04-Jun-2024
Physical Peramenters