Administrative Approval Detail : 1568/।।।(2)/21-39(एम0एल0ए0)/2017 दिनांक 15.06.2021
TS Amount (lakhs) : 121.63 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
121.63
Resanction Cost :
121.63
Tentative Cost :
121.63
Exp. Upto Last Fy :
111.38
For CFY 2024-2025
Remaining :
10.25
Demand :
1.75
Allotment :
10.25
Exp in CFY :
0.00
Total Up to Date Exp :
111.38
In Maintenance After Completion
Sanction on : 3 years 6 months ago
15 Jun 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 7 months ago
28 Apr 2022
Actual Completion Date : 2 years 7 months ago
28 Apr 2022
Physical Linear Components
Remark
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: