Work Profile Report [125W359]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1568/।।।(2)/21-39(एम0एल0ए0)/2017 दिनांक 15.06.2021
TS Amount (lakhs) : 121.63 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
121.63
Resanction Cost :
121.63
Tentative Cost :
121.63
Exp. Upto Last Fy :
114.32
For CFY 2025-2026
Remaining :
7.31
Demand :
1.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
114.32
In Maintenance After Completion
Sanction on : 3 years 11 months ago
15 Jun 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 2 weeks ago
28 Apr 2022
Actual Completion Date : 3 years 2 weeks ago
28 Apr 2022
Physical Linear Components
Remark
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand