Work Profile Report [127W139]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : I/211307/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
39.38
Resanction Cost :
39.38
Tentative Cost :
39.38
Exp. Upto Last Fy :
21.39
For CFY 2025-2026
Remaining :
17.99
Demand :
17.99
Allotment :
17.89
Exp in CFY :
17.89
Total Up to Date Exp :
39.28
none
Sanction on : 1 year 2 months ago
15 May 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
100 %
Tentative Completion date on : 5 months 3 days ago
05 Mar 2025
Actual Completion Date : 5 months 3 days ago
05 Mar 2025
Physical Linear Components
Remark
कार्य पूर्ण -- as on 06-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand