Work Profile Report [129W682]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई-फाईल सं0-48594, दिनांक 19.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 29.42 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.42
Resanction Cost :
29.42
Tentative Cost :
29.42
Exp. Upto Last Fy :
17.16
For CFY 2024-2025
Remaining :
12.26
Demand :
12.26
Allotment :
12.00
Exp in CFY :
12.00
Total Up to Date Exp :
29.16
Work completed
Sanction on : 1 year 4 months ago
19 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 6 months 2 weeks ago
06 May 2024
Actual Completion Date : 7 months 3 weeks ago
30 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष -- as on 18-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand