Work Profile Report [16W511]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 7209/।।।(2)/15-09(प्रा0आ0)/2014 दिनांक 17.10.2015
TS Amount (lakhs) : 492.98 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
492.98
Resanction Cost :
166.25
Tentative Cost :
39.89
Saving
126.36
Exp. Upto Last Fy :
39.89
For CFY 2024-2025
Remaining :
126.36
Demand :
12.00
Allotment :
12.42
Exp in CFY :
0.00
Total Up to Date Exp :
39.89
Construction Started
Sanction on : 9 years 2 months ago
17 Oct 2015
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
40 %
Tentative Completion date on : 2 months 2 days from now
28 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
निरस्तीकरण प्रस्ताव मुख्य अभियन्ता लो0नि0वि0,अल्मोड़ा के पत्रांक 2350/03 याता (नि01)-अ0/2023-24 दिनांक 05/2024 द्वारा प्रमुख अभियन्ता एवं विभागाध्यक्ष,लो0नि0वि0,देहरादून को प्रेषित। -- as on 05-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: