Work Profile Report [16W630]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : उत्तराखण्ड लोक निर्माण विभाग अनुभाग-2 के ई फाईल संख्या 51161 दिनांक 03 मई,2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
116.55
Resanction Cost :
116.55
Tentative Cost :
110.55
Saving
6.00
Exp. Upto Last Fy :
101.51
For CFY 2025-2026
Remaining :
15.04
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
101.51
In Maintenance After Completion
Sanction on : 1 year 11 months ago
03 May 2023
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
100 %
Tentative Completion date on : 5 months 1 week ago
30 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 10-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand