Work Profile Report [19W841]

सर्किट हाउस के विस्ताीकरण/उच्चीकरण/अनुरक्षण सम्बन्धी कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : इलेक्ट्रोनिक अभिलेख पत्रावली संख्या 01(तीन)(389)/2023 राज्य सम्पत्ति अनुभाग-01 दिनांक 15-03-2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

820.10

Resanction Cost :

820.10

Tentative Cost :

820.10

Exp. Upto Last Fy :

99.47

For CFY 2025-2026

Remaining :

720.63

Demand :

320.10

Allotment :

126.06

Exp in CFY :

126.06

Total Up to Date Exp :

225.53

Construction Started

Sanction on : 2 years 1 month ago

26 Sep 2023

Physical Progress:

At start of FY 2025-2026 :

15 %

Up to Date :

50 %

Tentative Completion date on : 1 month 4 days ago

30 Sep 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
0
1
0
0

Remark

view all

द्वितीय तल में ट्रस व ए0ए0सी0 ब्लाॅक का कार्य प्रगति, प्रथम तल में प्लास्टर का कार्य 95 प्रतिशत पूर्ण। भू-तल में प्लास्टर का कार्य पूर्ण। अन्य फिनिशिंग का कार्य प्रगति पर। -- as on 14-Oct-2025

Rating : 61

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: