Work Profile Report [1W583]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO letter no5248/III(2)/21-52(MLA)/2017 TC दिनांक 29-10-2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
51.30
Resanction Cost :
52.84
Tentative Cost :
52.84
Exp. Upto Last Fy :
40.41
For CFY 2024-2025
Remaining :
12.43
Demand :
2.50
Allotment :
5.75
Exp in CFY :
5.75
Total Up to Date Exp :
46.16
Work completed
Sanction on : 2 years 1 month ago
29 Oct 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 8 months ago
31 Mar 2023
Actual Completion Date : 1 year 8 months ago
31 Mar 2023
Physical Linear Components
Remark
कार्य्र पूर्ण माह 03/2023 दायित्व शेष। -- as on 11-May-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: