Work Profile Report [22W1581]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-file No. 83534/56, dt. 20.03.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
80.88
Resanction Cost :
80.88
Tentative Cost :
80.88
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
80.78
Demand :
60.00
Allotment :
10.44
Exp in CFY :
10.44
Total Up to Date Exp :
10.54
Construction Started
Sanction on : 5 months 1 week ago
20 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
40 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0, डब्ल्यू0बी0एम0 जी2, डब्ल्यू0बी0एम0 जी3 का कार्य 700 मी0 लम्बाई में पूर्ण, शेष लम्बाई में कार्य प्रगति पर। -- as on 29-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand