Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.83 | 1.83 | 1.83 | 0 |
Closed Work 25W1097 :
Administrative Approval Detail : शा0सं0 3603 /।।। (2)/ 21- 64 (एम0एल0ए0) /2017 टी0सी0।।। दि0 14.9.21
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
108.99
Resanction Cost :
108.99
Tentative Cost :
108.99
Exp. Upto Last Fy : 80.10
For CFY 2024-2025
Remaining : 28.89
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 80.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 85 %
Sanction on :
2 years 10 months ago
14 Sep 2021
Tentative Completion date:
1 year 7 months ago
13 Dec 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.50 किमी0 लम्बाई में कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 08-Dec-2022
Physical Peramenters