Administrative Approval Detail : शा0सं0 । /10569 /2023 (ई0 फाईल सं0 50224) दि0 28.3.23
TS Amount (lakhs) : 84.75 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
84.75
Resanction Cost :
84.75
Tentative Cost :
62.00
Saving
22.75
Exp. Upto Last Fy :
17.42
For CFY 2024-2025
Remaining :
67.33
Demand :
35.00
Allotment :
20.00
Exp in CFY :
9.19
Total Up to Date Exp :
26.61
Construction Started
Sanction on : 1 year 7 months ago
28 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
75 %
Tentative Completion date on : 3 months 12 hours from now
28 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य प्रगति में। -- as on 24-Aug-2024