Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
25W986 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2069/।।।(2)/16-64(एम0एल0ए0) /2016 दिनांक 30.6.2016
TS Amount (lakhs) : 52.95 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
52.95
Resanction Cost :
52.95
Tentative Cost :
52.95
Exp. Upto Last Fy : 1.26
For CFY 2024-2025
Remaining : 51.69
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.26
Work deferred
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 0 %
Sanction on :
8 years 2 weeks ago
30 Jun 2016
Tentative Completion date:
1 year 4 months ago
15 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: To Cancel
वन भूमि स्वीकृति हेतु प्रस्ताव भारत सरकार को प्रेषित किया गया था क्षतिपूर्ति वृक्षारोपण हेतु आवश्यक 8.60 है0 चयनित भूमि को भारत सरकार द्वारा वृक्षारोपण हेतु अयोग्य बताते हुए प्रकरण पुनः आपत्तियों में प्राप्त हुआ है क्षतिपूर्ति वृक्षारोपण हेतु अन्यत्र स्थान पर भूमि उपलब्ध कराने के सम्बन्ध में इस खण्ड एवं उच्चाधिकारियों द्वारा डी0एफ0ओ0 नैनीताल को अनेक बार पत्राचार किया जा चुका है परन्तु आतिथि तक भी आवश्यक भूमि उपलब्ध नहीं हो पायी है एवं निकट भविष्य में क्षतिपूर्ति वृक्षारोपण हेतु भूमि का मिलना भी सम्भव प्रतीत नहीं हो रहा है। प्रमुख अभियन्ता एवं विभागाध्यक्ष नियोजन-।। लो0नि0वि0 देहरादून का पत्रांक 192/01 (29)- व0भू0 -नि0-।।।/2024 दि0 23.02.24 के आदेशों के अनुपालन में विषयगत कार्य में 5 वर्ष से अधिक समय बीतने के उपरांत भी वन भूमि स्वीकृति प्राप्त न होने के कारण इस कार्य का निरस्तीकरण प्रस्ताव मुख्य अभियन्ता हल्द्वानी के पत्रांक 1630/01 याता (काशीपुर)- हल्द्वानी /2024 दि0 29.04.24 द्वारा उत्तराखण्ड शासन को प्रेषित किया जा चुका है। -- as on 30-May-2024
Physical Peramenters