Work Profile Report [30W1521]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : 212/III(2)/2024-01(Pra.Aa)/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
148.22
Resanction Cost :
148.22
Tentative Cost :
148.22
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
148.22
Demand :
110.93
Allotment :
58.00
Exp in CFY :
48.22
Total Up to Date Exp :
48.22
Work completed
Sanction on : 9 months 3 weeks ago
31 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
45 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 weeks ago
30 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 04-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: