Work Profile Report [43W1079]
Tenders
Project Activities
alerts
Administrative Approval Detail : e file 51381 dt 02-01-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
171.68
Resanction Cost :
171.68
Tentative Cost :
171.68
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
171.58
Demand :
171.00
Allotment :
40.53
Exp in CFY :
40.53
Total Up to Date Exp :
40.63
Construction Started
Sanction on : 7 months 6 days ago
02 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
10 %
Tentative Completion date on : 8 months 2 weeks from now
24 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर किमी0 01 मे G1 का कार्य पूर्ण । अवशेष भाग में कार्य प्रगति पर है । -- as on 04-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: