Work Profile Report [45W182]

घनसाली-मूलगढ-चिरबिटिया मोटर मार्ग के कि0मी0-17 थौलधार, सरोली-धारगांव-मयाली तक मोटर मार्ग का नव निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0 1542/।।।(2)/20-09(एम0एल0ए0)/2017टी0सी0,दि0-04.09.2020

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

14.19

Resanction Cost :

14.19

Tentative Cost :

14.19

Exp. Upto Last Fy :

1.22

For CFY 2024-2025

Remaining :

12.97

Demand :

0.10

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.22

Alignment Approved

Sanction on : 4 years 3 months ago

04 Sep 2020

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 2 years 8 months ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
0.000
4
0.000
0.000

Remark

view all

सर्वे कर दिया गया है, वनभूमि पत्रावली गठन का कार्य प्रगति पर। -- as on 04-Nov-2024

Rating : 9

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: