Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 |
56W567 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2702/।।। (2) /17-30 (प्रा0आ0)/2017 दिनांक 10.11.2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
152.00
Resanction Cost :
152.00
Tentative Cost :
152.00
Exp. Upto Last Fy : 2.87
For CFY 2024-2025
Remaining : 149.13
Demand : 0.40
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.87
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
6 years 8 months ago
10 Nov 2017
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
वनभूमि प्रस्ताव संख्या एफ0पी0/यू0के0/आर0के0/आर0ओ0/ए0डी0/44931/2020 के द्वारा गठित। भारत सरकार द्वारा झुल्का डांडा तक ही मार्ग बनाने के लिए निर्देश दिये गये है, जिसके कारण प्रस्ताव निरस्त किया गया है जिसके क्रम में प्रभागीय वनाधिकारी के पत्रांक 4877/12-1 दिनांक 01.05.2023 के क्रम में दिनांक 08.05.2023 को संयुक्त निरीक्षण के दौरान क्षेत्रीय ग्रामीणों एवं जनप्रतिनिधियों द्वारा वैकल्पिक समरेखण पर पुनः आमसहमति बनाकर तदानुसार अवगत कराने का अनुरोध किया गया हैं। -- as on 02-Jan-2024
Physical Peramenters