Work Profile Report [5W35]

जनपद बागेश्वर में जल्थाकोट चमडथल-किमोली मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शा0सं0 3138/101-2/06-61 (प्रा0आ0)/06दिनांक 22.11.2006

TS Amount (lakhs) : 142 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

142.00

Resanction Cost :

142.00

Tentative Cost :

142.00

Exp. Upto Last Fy :

105.50

For CFY 2024-2025

Remaining :

36.50

Demand :

12.10

Allotment :

10.00

Exp in CFY :

7.10

Total Up to Date Exp :

112.60

Construction Started

Sanction on : 17 years 8 months ago

22 Nov 2006

Physical Progress:

At start of FY 2024-2025 :

45 %

Up to Date :

45 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
8
8
1.600
6.4
0.000
0.000

Remark

view all

1.60 किमी0 पहाड़ कटान कार्य पूर्ण। 1.60 किमी0 पार्ट-।। कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 02-Apr-2024

Rating : 79

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: