Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.125 | 2.125 | 0.000 | 2.125 | 0.000 | 0.000 |
69W309 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली संख्या -36087, लोक निर्माण अनुभाग-2 दि0 10 नवम्बर 2022
TS Amount (lakhs) : 116.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
116.35
Resanction Cost :
121.94
Tentative Cost :
121.94
Exp. Upto Last Fy : 66.57
For CFY 2024-2025
Remaining : 55.37
Demand : 45.00
Allotment : 60.01
Exp in CFY : 26.72
Total Up to Date Exp : 93.28
Construction Started
Physical Progress:
At start of FY 2024-2025 : 39 %
Up to Date : 85 %
Sanction on :
1 year 8 months ago
10 Nov 2022
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
PC का कार्य पूर्ण। -- as on 01-Jul-2024
Physical Peramenters