Work Profile Report [70W517]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-52638, दिनांक 26-02-2024
TS Amount (lakhs) : 30 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.00
Resanction Cost :
30.00
Tentative Cost :
30.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
30.00
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Survey work done
Sanction on : 5 months 3 weeks ago
26 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
20 %
Tentative Completion date on : 1 month 1 week from now
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वेक्षण कार्य पूर्ण। स्थल चयन की कार्यवाही प्रगति पर। -- as on 18-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: