Work Profile Report [8W13]

सुराईथोटा- तोलमा मोटर मार्ग का विस्तार (किमी॰ 3 से 4.50)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

  • Project Activities
  • alerts

    Documents

    Samples

Administrative Approval Detail : 1754/।।।-2/05-64(प्रा॰आ॰)/2005 दि॰ 10.11.05

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

21.60

Resanction Cost :

21.60

Tentative Cost :

21.60

Exp. Upto Last Fy :

4.08

For CFY 2024-2025

Remaining :

17.52

Demand :

1.50

Allotment :

1.50

Exp in CFY :

0.00

Total Up to Date Exp :

4.08

Alignment Approved

Sanction on : 19 years 1 month ago

10 Nov 2005

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

20 %

Tentative Completion date on : 3 months 6 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
1.5
1.5
1.5
-

Remark

view all

No objection certificate received from villagers. Joint visit with forest department proposed on 29.07.2024. -- as on 25-Jul-2024

Rating : 21

Forest Case Pending At : 04: DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand