Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
10W51 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 827/।।।- (2)/06-76 (प्रा0आ0)/05 टी0सी0 दि0 28/3/06
TS Amount (lakhs) : 35.6 Lacs
Financial Detail
Sanction Cost : 35.60 Lacs
Resanction Cost : 35.60 Lacs
Exp. Upto Last Fy : 28.00 Lacs
For CFY 2024-2025
Remaining : 7.60 Lacs
Demand : 7.60 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 28.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
18 years 1 month ago
28 Mar 2006
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण, शेष कार्य प्रगति में। आज दिनांक 26.04.2024 तक भी विधिवत स्वीकृ1ति अपेक्षित है। -- as on 06-May-2024
Physical Peramenters