Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
11W587 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक ई-फाईल संख्या 51071 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 90.15 Lacs
Resanction Cost : 90.15 Lacs
Exp. Upto Last Fy : 58.72 Lacs
For CFY 2024-2025
Remaining : 31.43 Lacs
Demand : 28.90 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 58.72 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
7 months 1 week ago
12 Oct 2023
Tentative Completion date:
3 weeks 4 days from now
14 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0 3 तक का कार्य पूर्ण। -- as on 10-Apr-2024
Physical Peramenters