Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 |
125W349 :
Administrative Approval Detail : शासनादेश संख्या 903(1)/।।।(2)/21-39(एम0एल0ए0)201टी0सी0 दिनांक 30.03.2021
TS Amount (lakhs) : 62.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
62.26
Resanction Cost :
62.26
Tentative Cost :
62.26
Exp. Upto Last Fy : 57.85
For CFY 2024-2025
Remaining : 4.41
Demand : 0.45
Allotment : 4.41
Exp in CFY : 0.00
Total Up to Date Exp : 57.85
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 3 months ago
30 Mar 2021
Tentative Completion date:
1 year 11 months ago
01 Aug 2022
Actual Completion Date:
2 years 1 week ago
07 Jul 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023
Physical Peramenters