Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.1 | 2.1 | 2.1 | 0 |
125W504 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 45543/2023 ई पत्रावली संख्या 48456 दिनांक 31.07.2023
TS Amount (lakhs) : 24.93 Lacs
Financial Detail
Sanction Cost : 24.93 Lacs
Resanction Cost : 24.93 Lacs
Exp. Upto Last Fy : 20.11 Lacs
For CFY 2024-2025
Remaining : 4.82 Lacs
Demand : 4.82 Lacs
Allotment : 4.49 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 20.11 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
6 days 20 hours from now
26 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 27-Oct-2023
Physical Peramenters