Work Profile Report [127W1]

श्री केदारनाथ धाम परिक्षेत्रान्तर्गत संगम घाट के पुनर्विकास का निर्माण कार्य (आई०ओ०सी०एल०)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks

    Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शासनादेश संख्या - 1739/VI(1)/2020-03(10)/2020

TS Amount (lakhs) : 1547.8 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

1548.11

Resanction Cost :

1548.11

Tentative Cost :

1548.11

Exp. Upto Last Fy :

697.75

For CFY 2024-2025

Remaining :

850.36

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

697.75

Construction Started

Sanction on : 3 years 10 months ago

28 Sep 2020

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

60 %

Tentative Completion date on : 2 years 2 weeks ago

31 Jul 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
0
1
1
0

Remark

view all

Rating : 60

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI: Garurchatti Bridge

© PWD Uttarakhand