Work Profile Report [127W11]

श्री केदारनाथ धाम परिक्षेत्रान्तर्गत प्रशासनिक कार्यालय व अस्पताल भवन का निर्माण कार्य (आर०ई०सी०)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शासनादेश संख्या - 1440/VI(1)/2020-03(18)/2020

TS Amount (lakhs) : 1999.12 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

1999.12

Resanction Cost :

2265.16

Tentative Cost :

2265.16

Exp. Upto Last Fy :

927.38

For CFY 2024-2025

Remaining :

1,337.78

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

927.38

Construction Started

Sanction on : 3 years 10 months ago

24 Sep 2020

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

60 %

Tentative Completion date on : 1 year 8 months ago

04 Dec 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Buildings
2
2
2
-

Remark

view all

Rating : 60

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: Garurchatti Bridge

© PWD Uttarakhand