Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.85 | 2.85 | 2.850 | 0 | 0.000 | 0.000 |
129W434 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 1222/।।।(2)/19-34(एम0एल0ए0)/ 2017 टी0सी0-1 लोक निर्माण विभाग-2, दिनांक 05.03.2019
TS Amount (lakhs) : 115.54 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
115.54
Resanction Cost :
121.09
Tentative Cost :
115.54
Saving
5.55
Exp. Upto Last Fy : 107.37
For CFY 2024-2025
Remaining : 13.72
Demand : 1.11
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 107.37
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
05 Mar 2019
Tentative Completion date:
Yet To Decide
Actual Completion Date:
2 years 3 months ago
30 Mar 2022
Remark
Bottelneck: no issue
कार्य पूर्ण -- as on 25-Apr-2023