Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14.3 | 14.3 | 14.300 | 0 | 0.000 | 0.000 |
129W648 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Govt. Order No. 1182/III(3)/21-41(CRIF)/2021 Dt. 27.10.2022
TS Amount (lakhs) : 2518.09 Lacs
Financial Detail
Sanction Cost : 2,518.09 Lacs
Resanction Cost : 2,518.09 Lacs
Exp. Upto Last Fy : 2,461.66 Lacs
For CFY 2024-2025
Remaining : 56.43 Lacs
Demand : 56.43 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2,461.66 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 6 months ago
27 Oct 2022
Tentative Completion date:
6 months 2 weeks ago
30 Oct 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 29-Feb-2024
Physical Peramenters