Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
12W41 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 2503 / ।।। (2) /2006-37 (प्रा0आ0) / 06 दिनांक 20.09.2006
TS Amount (lakhs) : 71.2 Lacs
Financial Detail
Sanction Cost : 71.20 Lacs
Resanction Cost : 71.20 Lacs
Exp. Upto Last Fy : 55.71 Lacs
For CFY 2024-2025
Remaining : 15.49 Lacs
Demand : 15.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 55.71 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
17 years 7 months ago
20 Sep 2006
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
3.50 किमी0 पहाड़ कटान कार्य पूर्ण। 3.50 किमी0 पर ग्रामवासियों द्वारा पूर्व निर्मित हल्का वाहन मार्ग पर मिल जाने के कारण आगे मोटर मार्ग बनाने की आवश्यकता नहीं है। प्रतिकर प्रस्वाव गठित। अवशेष प्रतिकर भुगतान हेतु समाचार पत्र के माध्यम से कास्तकारों को सूचना पे्रषित की गई है। -- as on 02-Apr-2024
Physical Peramenters