Administrative Approval Detail : RO/UK/12014/108/Annual Plan/2019-20 dt 12.02.2020 Job No. NH -125(09)-UR-2019-20-554 dated 18.02.2020
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3629.91
Resanction Cost :
3629.91
Tentative Cost :
3629.91
Exp. Upto Last Fy :
2,129.04
For CFY 2024-2025
Remaining :
1,500.87
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2,129.04
Work completed
Sanction on : 4 years 10 months ago
18 Feb 2020
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 7 months ago
13 May 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3
Bridges on The Basis of AI: Pooled Aawash approach road Rcc bridge RCC MOTOR Bridge Over Batel River