Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 43 | 43 | 43.000 | 0 | 0.000 | 0.000 |
No of Bridges | 8 | 11 | 7 | 4 | 0 | 0 |
Span of Bridges [m] | 856.5 | 940 | 0.000 | 940 | 0.000 | 0.000 |
139W3 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Steel girder bridge in km 1.00 at kakraligate thuligarh motor road
Administrative Approval Detail : Government of India, Directorate General of works C.P.W.D., 433-B, A-wing, Nirman Bhawan, New Delhi (BFR Cell) vide letter no. DGW/BFR/32nd HLEC/2016-17/580 Dated 18-08-2016 for Rs. 252.81 crore.
TS Amount (lakhs) : 35101 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25281.00
Resanction Cost :
30808.00
Tentative Cost :
30808.00
Exp. Upto Last Fy : 21,377.57
For CFY 2024-2025
Remaining : 9,430.43
Demand : 4,051.00
Allotment : 0.00
Exp in CFY : 17.41
Total Up to Date Exp : 21,394.97
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
7 years 10 months ago
18 Aug 2016
Tentative Completion date:
1 year 1 week from now
25 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
work is executed in 3 no. of packages
Package I - Km 12.000- km 29.875 Work Completed
Package II - Km 30.565 - Km 55.000 Work Completed
Package III - 690 mtr bridge in Km 30 and 31 Work Start
-- as on 09-May-2024
Physical Peramenters