Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
16W303 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2520/।।।(2)/16-64(प्रा0आ0)/2016 दिनांक 18.10.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 18.18 Lacs
Resanction Cost : 18.18 Lacs
Exp. Upto Last Fy : 0.37 Lacs
For CFY 2024-2025
Remaining : 17.81 Lacs
Demand : 0.15 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.37 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
7 years 7 months ago
18 Oct 2016
Tentative Completion date:
6 years 1 month ago
31 Mar 2018
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
वन भूमि प्रस्ताव डी0एफ0ओ0 से आपत्तियों में प्राप्त। आपत्तियो के निराकरण हेतु अधिशासी अभियन्ता के पत्रांक 950/3सी0 दिनांक 12.04.2024 द्वारा आई0टी0 सैल देहरादून को पुनः क्षतिपूरक वृक्षारोपण के जियो रिफरेन्स मैप बनाने हेतु पत्र प्रेषित किया गया है। -- as on 30-Apr-2024
Physical Peramenters