Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 11 | 9.200 | 1.8 | 1.800 | 0.000 |
16W376 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 775/।।।(2)/16-11(प्रा0आ0)/2011 दिनांक 09.02.2016
TS Amount (lakhs) : 605.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
605.61
Resanction Cost :
605.61
Tentative Cost :
605.61
Exp. Upto Last Fy : 318.69
For CFY 2024-2025
Remaining : 286.92
Demand : 100.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 318.69
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
8 years 5 months ago
09 Feb 2016
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अवशेष कार्य हेतु पुनः निविदा दिनांक 10.06.2024 को आमंत्रित की गई, जो दिनांक 09.07.2024 को खोली जानी थी। अपरिहार्य कारणों से अब दिनांक 19.07.2024 को खोली जायेगी। -- as on 13-Jul-2024
Physical Peramenters