Work Profile Report [16W376]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 775/।।।(2)/16-11(प्रा0आ0)/2011 दिनांक 09.02.2016
TS Amount (lakhs) : 605.61 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
605.61
Resanction Cost :
605.61
Tentative Cost :
605.61
Exp. Upto Last Fy :
318.69
For CFY 2024-2025
Remaining :
286.92
Demand :
100.00
Allotment :
58.97
Exp in CFY :
58.97
Total Up to Date Exp :
377.66
Construction Started
Sanction on : 9 years 1 month ago
09 Feb 2016
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
75 %
Tentative Completion date on : 11 months 2 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.50 किमी0 लम्बाई में पार्ट-।। का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 02-Jan-2025