Work Profile Report [16W565]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : NDMA के पत्र संख्या - F.No. 6-9/2011 (Mit) एवं अपर मुख्य कार्यकारी अधिकारी, उत्तराखण्ड राज्य आपदा प्रबन्धन प्राधिकरण, सचिवालय परिसर, देहरादून 934/USDMA-685(2019)
TS Amount (lakhs) : 8.3432 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
834.32
Resanction Cost :
834.32
Tentative Cost :
834.32
Exp. Upto Last Fy :
327.62
For CFY 2024-2025
Remaining :
506.70
Demand :
0.00
Allotment :
0.35
Exp in CFY :
0.35
Total Up to Date Exp :
327.97
Work completed
Sanction on : 5 years 5 months ago
12 Jul 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 6 months ago
05 Jun 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 07-Jan-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Bailey Bridge (Sh11) Km 165.800