Work Profile Report [1W377]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शा0 संख्या 2008/।।।(2)/16-53(एम0एल0ए0) /2015 दिनांक 27 जून, 2016
TS Amount (lakhs) : 165.29 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
165.29
Resanction Cost :
165.29
Tentative Cost :
165.29
Exp. Upto Last Fy :
165.40
For CFY 2024-2025
Remaining :
-0.11
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
165.40
In Maintenance After Completion
Sanction on : 8 years 4 months ago
27 Jun 2016
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 7 months ago
31 Mar 2022
Actual Completion Date : 3 years 1 month ago
30 Sep 2021
Physical Linear Components
Remark
कार्य पूर्ण माह 03/2022 -- as on 11-May-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: