Work Profile Report [1W564]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO letter no 571(I)/X-3(MLA)/2020-21 दिनांक 06-10-2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
372.68
Resanction Cost :
372.68
Tentative Cost :
372.68
Exp. Upto Last Fy :
243.47
For CFY 2024-2025
Remaining :
129.21
Demand :
0.00
Allotment :
121.18
Exp in CFY :
139.58
Total Up to Date Exp :
383.05
Work completed
Sanction on : 3 years 1 month ago
06 Oct 2021
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
100 %
Tentative Completion date on : 9 months 1 week ago
15 Feb 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। कार्य वास्तविक रूप से 28/02/2024 को पूर्ण हो चुका है। दायित्व अवशेष। -- as on 06-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: