Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 10.000 | -5 | 0.000 | 0.000 |
1W567 :
Administrative Approval Detail : शासन का पत्राक 3602 /III (2)/48/((प्रा०आ०)/2018 dated14-09-2021
TS Amount (lakhs) : 334.03 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
334.03
Resanction Cost :
334.03
Tentative Cost :
334.03
Exp. Upto Last Fy : 308.12
For CFY 2024-2025
Remaining : 25.91
Demand : 2.00
Allotment : 1.50
Exp in CFY : 0.21
Total Up to Date Exp : 308.33
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
14 Sep 2021
Tentative Completion date:
10 months 2 days ago
15 Sep 2023
Actual Completion Date:
8 months 2 weeks ago
31 Oct 2023
Remark
Bottelneck: no issue
निर्माण कार्य पूर्ण। दायित्व शेष। -- as on 30-Jun-2023
Physical Peramenters