Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 2.500 | 0.5 | 0.500 | 0.000 |
1W589 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 39707 दिनंाक 14-02-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
90.15
Resanction Cost :
90.15
Tentative Cost :
90.15
Exp. Upto Last Fy : 40.53
For CFY 2024-2025
Remaining : 49.62
Demand : 10.00
Allotment : 0.00
Exp in CFY : 1.61
Total Up to Date Exp : 42.14
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
1 year 5 months ago
14 Feb 2023
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
1 month 2 days ago
15 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण माह 06/2024 दायित्व शेष। -- as on 03-Jul-2024
Physical Peramenters