Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 3.000 | 1 | 1.000 | 0.000 |
1W69 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 764/।।।(2)/08-65(प्रा0आ0)/07 दिनंाक 24.03.2008
TS Amount (lakhs) : 140 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
140.00
Resanction Cost :
140.00
Tentative Cost :
140.00
Exp. Upto Last Fy : 82.08
For CFY 2024-2025
Remaining : 57.92
Demand : 57.92
Allotment : 20.00
Exp in CFY : 0.00
Total Up to Date Exp : 82.08
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 month 2 days ago
15 Jun 2024
Remark
Forest Status 21: Final
Bottelneck: no issue
कार्य पूर्ण माह 06/2024 दायित्व शेष। -- as on 03-Jul-2024
Physical Peramenters