Work Profile

1W69 :

No Pic Avilable Time series Gantt
शीतालाखेत कठपुड़िया मोटर मार्ग से बटगल भट्ट (मल्ला) तक मोटर मार्ग


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0 764/।।।(2)/08-65(प्रा0आ0)/07 दिनंाक 24.03.2008

TS Amount (lakhs) : 140 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

140.00

Resanction Cost :

140.00

Tentative Cost :

140.00

Exp. Upto Last Fy : 82.08

For CFY 2024-2025

Remaining : 57.92

Demand : 57.92

Allotment : 20.00

Exp in CFY : 0.00

Total Up to Date Exp : 82.08

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
16 years 3 months ago
24 Mar 2008


Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024


Actual Completion Date:
1 month 2 days ago
15 Jun 2024


Rating : 100

Remark

Forest Status 21: Final

Bottelneck: no issue


कार्य पूर्ण माह 06/2024 दायित्व शेष। -- as on 03-Jul-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 4 4 3.000 1 1.000 0.000
Currently only Bank Gaurantee information is avilable