Work Profile Report [23W1225]
Remarks
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : G.O. no.- I/139122/2023 e-file no.- 51571
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
161.98
Resanction Cost :
161.98
Tentative Cost :
161.98
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
161.98
Demand :
160.00
Allotment :
58.96
Exp in CFY :
109.46
Total Up to Date Exp :
109.46
Construction Started
Sanction on : 1 year 4 months ago
20 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
20 %
Tentative Completion date on : 3 months 3 weeks from now
15 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 02-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: