Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 0.000 | 1.2 | 1.200 | 0.000 |
23W1225 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/139122/2023 e-file no.- 51571
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
161.98
Resanction Cost :
161.98
Tentative Cost :
161.98
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 161.98
Demand : 150.00
Allotment : 0.00
Exp in CFY : 58.13
Total Up to Date Exp : 58.13
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
11 months 3 weeks ago
20 Jul 2023
Tentative Completion date:
7 months 4 weeks from now
15 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters