Work Profile Report [23W1240]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : G.O. no.- I/230521/2024, e-file no.- 53091
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
216.29
Resanction Cost :
216.29
Tentative Cost :
216.29
Exp. Upto Last Fy :
130.64
For CFY 2025-2026
Remaining :
85.65
Demand :
85.65
Allotment :
66.18
Exp in CFY :
66.18
Total Up to Date Exp :
196.82
Work completed
Sanction on : 1 year 2 months ago
06 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
100 %
Tentative Completion date on : 5 months 3 days ago
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 24-Sep-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand