Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
Closed Work 25W1063 :
Administrative Approval Detail : शा0सं0 1428(।)/।।।(2)/21-62(एम0एल0ए0)/2017 दिनांक 2.6.2021
TS Amount (lakhs) : 51.95 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
51.95
Resanction Cost :
51.95
Tentative Cost :
51.95
Exp. Upto Last Fy : 51.95
For CFY 2024-2025
Remaining : 0.00
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 51.95
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
02 Jun 2021
Tentative Completion date:
1 year 4 months ago
15 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 08-Dec-2022
Physical Peramenters