Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 1.8 | 0.000 | 1.8 | 1.800 | 0.000 |
25W1127 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /10569 /2023 (ई0 फाईल सं0 50224) दि0 28.3.23
TS Amount (lakhs) : 84.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
84.75
Resanction Cost :
84.75
Tentative Cost :
84.75
Exp. Upto Last Fy : 17.42
For CFY 2024-2025
Remaining : 67.33
Demand : 35.00
Allotment : 10.00
Exp in CFY : 0.96
Total Up to Date Exp : 18.38
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 75 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य प्रगति में। -- as on 27-Jun-2024