Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 24 | 24 | 24 | 0 |
Closed Work 30W1108 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Dhanari pedestrain bridge
Administrative Approval Detail : 1643/।।।(2)/18-03 (एम0एल0ए0)/2017 टी0सी0 दि0 24-04-18
TS Amount (lakhs) : 354.29 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
318.86
Resanction Cost :
318.86
Tentative Cost :
318.86
Exp. Upto Last Fy : 316.87
For CFY 2024-2025
Remaining : 1.99
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 316.87
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
6 years 2 months ago
24 Apr 2018
Tentative Completion date:
1 year 11 months ago
30 Jul 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग चैड़ीकरण एवं दीवारों/स्कपरों का कार्य पूूर्ण हो चुका है। जी-1, जी-2 एवं जी-3 का कार्य 100 प्रतिशत पूर्ण। पी0सी0 का कार्य 1.80 किमी0 तक पूण। पुल के ऐबटमेंट का कार्य पूर्ण। 24मी0 विस्तार 1.50 लेन स्टील गर्डर सेतु का कार्य पूर्ण। एप्रोच का कार्य पूर्ण। -- as on 07-Sep-2022
Physical Peramenters