Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 3.500 | 0.000 |
30W1249 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 104/रा0यो0आ0/जि0यो0/2020-21 दि0 05-11-20
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
336.67
Resanction Cost :
336.67
Tentative Cost :
336.67
Exp. Upto Last Fy : 0.51
For CFY 2024-2025
Remaining : 336.16
Demand : 3.00
Allotment : 1.49
Exp in CFY : 0.00
Total Up to Date Exp : 0.51
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
3 years 8 months ago
05 Nov 2020
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
वनभूमि प्रस्ताव गठन की कार्यवाही की जा रही है। -- as on 03-Mar-2023
Physical Peramenters